Project :
Energy Performance Contract (EPC) between Politeknik Taiace Engineering Sdn Bhd and Sultan Azlan Shah in a mutually agreed ratio profit sharing of 80%:20% respectively for a period of eighty (80) months.
Building Information:
Gross Floor Area (GFA) : 97,975m2
Number of building blocks: 26
Average electricity consumption/month: 416,470kWh
Average maximum demand: 1,780kW
Number of students: 4,704 Number of staff: 411 (June 2014)
List of Energy Conservation Measure (ECM) :
1. Installation Voltage Optimization Units -Power Quality Devices
2. T8 Flourescent Light Bulb Replacement
3. HPSV Street Light & Garden Light Replacement
4. High Efficiency Split Unit Air Conditioner Installation
5. WCPU/ACPU Retrfit - Installation of Advance Thermal Control System.
TNB Tariff Rate:
Baseline Period Tariff Rate
Energy = RM0.365/kWh
Maximum Demand=RM30.30/kW
Cost Saving
Energy Saving in June 2015
= Saving + Maximum Demand (MD)
= (114, 791.29 kWh X RM0.365) + (-102kW x RM30.30)
= RM38,808.22 @ 26%
Energy Saving in July 2015
= Saving + Maximum Demand (MD)
= (110, 388.71 kWh X RM0.365) + (175kW x RM30.30)
= RM45,594.38 @ 25%
Energy Saving in August 2015
= Saving + Maximum Demand (MD)
= (101,467.54 kWh X RM0.365) + (175kW x RM30.30)
= RM46,405.64 @ 27%
Average energy savings for 3 months:
= Saving + Maximum Demand (MD)
= (109,110.53 kWh X RM0.365) + (125kW x RM30.30)
= RM43,602.74 @ 26%
The Next EPC projects at Polytechnics. (2015/2016)
- Politeknik Port Dickson
- Politeknik Sultan Salahuddin Abdul Aziz Shah (PSA)
- Politeknik Ibrahim Sultan (PIS)
- Politeknik Sultan Azlan Shah (PSAS)
- Politeknik Tuanku Sultanah Bahiyah (PTSB)
- Politeknik Tuanku Syed Sirajuddin (PTSS)
- Politeknik Seberang Perai (PSP)